2.7 KiB
Project State
Project Reference
See: .paul/PROJECT.md (updated 2026-05-07)
Core value: Sprzedawca moze obslugiwac zamowienia ze wszystkich kanalow sprzedazy i nadawac przesylki bez przelaczania sie miedzy platformami. Current focus: v3.7 Invoices + operational integrations - Phase 117 SMSPLANET settings/test SMS unified; migration/live SMS verification remains environment-dependent.
Current Position
Milestone: v3.7 Invoices (Fakturownia integration) - In progress Phase: 117 of TBD (SMSPLANET Integration Settings + Test SMS) - Complete Plan: 117-01 unified Status: Phase 117 complete; migration/manual SMS test pending because local DB is unavailable Last activity: 2026-05-12 - Unified SMSPLANET settings/test integration
Progress:
- Milestone v3.7: [########--] ~80% (Phase 113 + 114 + 115 + 116 + 117 closed; environment verification gaps documented)
- Phase 117: [##########] 100% - Implementation unified; migration/live SMS verification pending externally
Loop Position
Current loop state:
PLAN -> APPLY -> UNIFY
done done done [Phase 117 closed with environment gaps documented]
Session Continuity
Last session: 2026-05-12
Stopped at: Phase 117 unified; local migration/manual SMS verification pending
Next action: Start local MySQL, run C:\xampp\php\php.exe bin\migrate.php, verify SMSPLANET settings/test SMS, then plan the next v3.7 candidate or close the milestone.
Resume file: .paul/phases/117-smsplanet-integration/117-01-SUMMARY.md
Git State
Last phase commit: feat(117): smsplanet integration settings Branch: main
Pending Actions
- Manualne testy AC-1..AC-7 dla Phase 112 na zywej bazie (XAMPP online).
- Backfill zamowienia #882 - operator robi recznie po wdrozeniu (poza zakresem planu).
- Uruchom migracje gdy XAMPP online:
php bin/migrate.php(delivery_statuses). - Recznie odtworzyc istniejace reguly automatyzacji z grupowymi kluczami (BREAKING z 108-02).
- HostedSMS inbound replies: requires DCS/HostedSMS activation before implementation.
- Phase 117 follow-up: run migration when XAMPP MySQL is online and manually test real SMSPLANET sends for Bearer token and key + password.
Deferred to Next Milestones
- Phase 68 - Code Deduplication Refactor (0/2 Planning, nigdy nie rozpoczety).
- STAT-NET - netto shopPRO z API lub z
order_items.tax_rate(.paul/TODO.md). - Mobile Orders List / Mobile Order Details / Mobile Settings.
- INDEX-106-01 - indeksy DB dla query
customer_returned_count:order_addresses(order_id, address_type),shipment_packages(order_id, delivery_status)(gdy dataset >50k wierszy).
Skill Requirements
sonar-scannerrequired after APPLY; Phase 116 and Phase 117 gaps documented because CLI was not available in PATH.